Application-first concrete fibre engineering[email protected] · WhatsApp +86 159 6543 3989
Underground shotcrete working scene
MINING GROUND SUPPORT

For mining ground support:
synthetic fibre-reinforced
shotcrete.

Define the working face and spraying conditions first,
then connect the candidate fibre, testing and supply.

APPLICATION CONTEXTApplication image; not evidence of a Conchip project
01 Support conditions02 Spraying process03 Testing and acceptanceStart with site conditions
START AT THE WORKING FACE

Do not start with
"How many kilograms per cubic metre?"
Describe the site first.

Mining ground support is more than a material purchase. Evaluate the fibre within the complete support system and the actual spraying operation.

Design boundaryThe combination of bolts, mesh, shotcrete and other support elements must be determined by the project support design and qualified technical personnel.
01

What must the support do?

Ground and excavation conditions, excavation use, support stage, existing support elements and design requirements.

Support duty
02

How will the shotcrete be applied?

Wet- or dry-mix process, equipment and lines, nozzle constraints, dosing and mixing, and site operating conditions.

Process and equipment
03

How will acceptance be decided?

Layer thickness and early-strength requirements, construction records, specified test methods, result sources and approval procedures.

Acceptance basis
04

How will trials and supply be planned?

Site trial plan, dosage to evaluate, quantity, destination, timing and required documents.

Trial and supply plan
TWO PROCESSES. DIFFERENT CONTROL POINTS.

Both are shotcrete.
The control points differ.

Confirm the actual equipment and mixing route first.
Do not transfer wet-mix mixing requirements directly to dry-mix work.

  1. 01

    Dose by mass

    Calculate the fibre mass from the concrete volume per batch and the dosage being evaluated.

  2. 02

    Disperse in the wet mix

    Check the dosing sequence, mixing conditions and fibre dispersion.

  3. 03

    Check pumping and spraying

    Plan equipment and site trials around the actual lines, nozzle and working conditions.

  4. 04

    Record before evaluating

    Keep the mix, dosage, construction observations and specified tests in the same record.

Wet-mix control pointsDosing · dispersion · pumping / nozzle compatibility · spraying observations · project acceptance
  1. 01

    Dose fibres and dry materials

    Determine the fibre and dry-material masses from the mix being evaluated.

  2. 02

    Dry-mix uniformly first

    Dry-mix the fibres with cement, sand and aggregate uniformly, checking the actual equipment conditions.

  3. 03

    Add water at the nozzle

    Check nozzle operation, water control and actual spraying conditions separately.

  4. 04

    Verify for the project

    Retain site mixing, spraying observations and acceptance-test records.

Dry-mix control pointsDry mixing · nozzle water · operating conditions · spraying observations · project acceptance

TDS Rev. 20260701: water-soluble film bundles; standard cartons of 5 kg or 10 kg net. Dose by mass. For wet mix, continue mixing for 3–5 minutes after adding the fibres, or until uniform dispersion is confirmed. For dry mix, check the actual equipment and operating conditions.
This diagram organizes control points for project discussion. It does not replace equipment procedures, safety requirements or support design, and does not guarantee a particular site result.

THE FIBRE TO EVALUATE FIRST

For this application,
start with this candidate.

A priority candidate is not a final selection.
The product page remains the source for complete specifications and controlled documents.

White, indented High Strength Shotcrete 48 fibres in bundled formActual product photograph
Mining / tunnel shotcrete · priority candidate for evaluation

High Strength
Shotcrete 48

100% virgin polypropylene fibre with an indented surface. A candidate for project evaluation in mine roadways, tunnels and other shotcrete operations.

Length
48 mm
Equivalent diameter
0.7 mm
Tensile strength
≥570 MPa

These are confirmed nominal fibre specifications, not site concrete or support-performance results.

TDS suggested dosage range4–8 kg/m³

Final dosage depends on project design, mix, equipment and testing. Dosage alone does not establish energy absorption or residual strength.

View specifications, TDS and SDS
EVIDENCE THAT STAYS WITH THE CONDITIONS

Testing must stay
connected to site conditions.

When energy absorption needs evaluation, first define the specified method and acceptance requirements, then organize specimens, testing and review of the results.

Explore ground-support test dataEngineers: discuss the acceptance specification
PROJECT EVIDENCE RECORDMethod / conditions / source
01 / METHOD

Define what is measured and how it is accepted

Use the project-specified test method. EN 14488-5 is a method reference here; it does not mean this product has performance certification under that method.

02 / RECORD

Keep results with the sample, mix and dosage

Retain product and batch identity, specimen preparation and curing, mixing and spraying conditions, test records and data sources.

03 / CONCLUSION

State only the conditions the evidence covers

One set of results cannot be extended directly to every mining condition. Fibre tensile strength cannot be used to derive support performance.

Laboratory boundary

Conchip operates a factory-internal laboratory; it is not accredited. Internal data are for reference and project discussion. Arrange independent third-party testing when accredited evidence is required.

BEFORE THE FIRST TRIAL

Before a trial,
answer these three questions.

Can the fibre replace steel fibres or mesh at a fixed ratio?

There is no fixed substitution ratio for every mine. Changes to the support-material combination depend on project design, specifications and targeted verification, not the product name or dosage alone.

Can concrete grade and dosage alone predict performance?

No. The mix, fibre identity, wet- or dry-mix route, equipment, specimen preparation and curing, specified method and acceptance conditions are also needed.

What can I provide for the first technical discussion?

Start with the existing site conditions and project requirements. We can review the current product TDS, SDS and method information. Any specific test records must actually exist and be authorized for the intended use.

START A USEFUL TECHNICAL CONVERSATION

Send the conditions first.
Then discuss selection and trials.

You do not need every parameter finalized.
Send what is available and identify the conditions still to be confirmed.

Send mining project conditions Use the existing Project / Technical Inquiry route.
MINING PROJECT BRIEFFirst-discussion checklist
  1. 01Mine / roadway conditions and support duty
  2. 02Wet or dry mix, equipment and spraying conditions
  3. 03Mix, dosage to evaluate and trial plan
  4. 04Layer thickness, early strength and acceptance requirements
  5. 05Specified test method and available records
  6. 06Quantity, destination, timing and document needs
PROCUREMENT & SUPPLY

Continue according to
your purchasing task.

Technical procurement

List the formal product name, TDS / SDS version, intended conditions, trial quantity and supply quantity for review against the project specification.

Discuss the product specification →