An underground car park at a residential development in Shanghai used 50 mm Twist Wave fibre in the concrete base layer, with decorative stone panels installed above it. The recorded project dosage was 5 kg/m³, and approximately 50 tonnes of fibre were used.
Discuss base-layer samples and a site trial
- Twist Wave fibre
- 50 mm
- Base-layer project dosage
- 5 kg/m³
- Project quantity
- Approx. 50 tonnes
From sample submission to product selection
The project was designed by a design institute, and the flooring subcontractor contacted the supplier. Conchip first provided a product test report for Twist Wave 50 and fibre samples. The subcontractor completed a site trial before the product was formally selected.
When reviewing the trial area, the first step is to confirm which layer contains the fibre. The product named in the test report should then be matched to the supplied fibre and the trial mix. Base-layer thickness, level and any crack-control criteria should be checked against the project requirements. The decorative stone finish should be assessed against its own installation and acceptance records.
- Product test report and fibre samples
- Site trial
- Product selection
Product and technical resources
Twist Wave 50 product test report JCBG(01)250205945 · Test standard GB/T 21120-2018